General description of the project
Project’s purpose: reliability and quality supply improvement through modernization of substations, dispatching offices and control systems; competition level development by means of creation conditions for stable functioning of a wholesale power market and transmission network access improvement; operational expenses decrease; increase of provided services by “KEGOC” JSC
Description of “Promstroy-Energo” scope of works
Replacement of high-voltage equipment and reinstallation of OHTL overhangs on substations and main power transmission lines of “KEGOC” JSC:
- “Central MPN (Main Power Networks) branch of “KEGOC” JSC (Karagandinskaya area, 2004-2005):
- "Balkhash" SS-220kV,
- "Metallurgicheskaya" SS-220kV,
- "Nikolskaya" SS-220kV,
- "Akchatau" SS-220kV,
- "Kayrakty" SS-220kV;
- “Sarbayskie Intersystem Electric Network” branch of “KEGOC” JSC (Kostanayskaya area, 2004-2005):
- "Socol" SS-220kV,
- "Sarbayskaya” SS-220kV ,
- "Lisakovskaya" SS-220kV,
- "Kachary" SS-220kV;
- “Akmolinskie Intersystem Electric Network” branch of “KEGOC” JSC:
- "Main Center step-down substation" SS-220kV,
- “Atbasarskaya" SS-220kV,
- "Makinskaya" SS-220kV,
- "Krasnoarmeyskaya" SS-220kV,
- "Buran" SS-220kV (Akmolinskaya area).
|